Portfolio

Cell-Crete-Bay-Park-Pinole-1-1200x900.jpg

Bay Park, Pinole, CA

About The Project

PROJECT LOCATION

Pinole, California

A heavy rainfall event washed away a significant portion of the hillside. Unfortunately, this was close to a retirement home in the town of Pinole, CA. The hillside fell away from the building and ended up taking along a large section of the parking lot. As an effort to rebuild the area, lightweight cellular concrete (LCC) was proposed as a lightweight fill material preventing any future rainfall events from threatening the structure.

LCC is a strong candidate for fill material when faced with slide repair. The low-density material does not add excess load to the hillside and can safely rebuild for active traffic or vehicle storage.

The Solution

For the Bay Park project in Pinole, a gravity wall system was installed corresponding to each lift of LCC. A uniaxial geogrid was installed between lifts to add rigidity and strength to the wall and LCC structure. The final depth of the LCC fill was 20’ and achieved in 2’–3’ lifts over the course of 9 days.

Cell-Crete-Pipeline-4-project-1-1200x900.jpg

Pipeline 4 Relining, Lake Murray

About The Project

PROJECT LOCATION

San Diego, California

COMPLETION DATE

2017

Existing waterline prestressed concrete cylinder pipes (PCCP) required reinforcement.

The Solution

The waterline is set to be reinforced with new steel lining, and the steel liner is then placed in segments and welded together inside of the pipe, leaving a small annular space behind. Intimate contact between the host pipe and carrier pipe is required. Cellular concrete is being used to fill the annular space that varies from 1.5″ to 3″, and grouting takes place from inside the pipeline through grout ports prefabricated in the steel liner.

Cell-Crete-I-105-Project-5-1200x800.jpg

I-105 Willamette Connector

About The Project

PROJECT LOCATION

Eugene, Oregon

CLIENT

Oregon Department of Transportation (ODOT)

COMPLETION DATE

2018

Originally specified as an imported fill under an existing bridge span, low-density cellular concrete (LDCC) was specified as an addendum to the I-105 Willamette Connector Project. After consultation with general contractors in the region, it became obvious that with the timing, height constraints and anticipated settlement during construction, using an imported fill would then become difficult. An alternative of using low-density cellular concrete was proposed as a means to reduce the timeframe, reduce settlement during construction (using LDCC’s reduced weight) and using LDCC’s nocompaction properties to fill under the bridge span.

The Solution

Like every job, safety is always the top priority. The ability to pump LDCC reduced equipment constraints of working under an active highway along with the tight conditions between girders. Safety concerns regarding fall protection were addressed with the general contractor prior to placement of the LDCC.

LDCC was placed in 1–2 foot lifts in stair-stepped fashion until flushed with the top of the abutments. The project was completed in 10 days at the very beginning of the job to start the process of removing girders. Imported fill was used up to the pavement section of the roadway.

Cell-Crete-Mid-Coast-Corridor-Project-1-1200x900.jpg

Mid-Coast Transit Corridor, San Diego, CA

About The Project

PROJECT LOCATION

San Diego, California

COMPLETION DATE

Ongoing

A double track for the Burlington Northern and Santa Fe (BNSF) Railway is being constructed at the San Diego River Bridge. The Mid-Coast Transit Corridor project is being built in two stages to keep the track operating throughout construction.

The Solution

Cellular concrete is being used to raise the track’s elevation and also being added in between full-height Mechanically Stabilized Earth (MSE) panels due to the access on either side of the wall.

LPCH_1078-1200x900.jpg

Lucile Packard Children’s Hospital

About The Project

PROJECT LOCATION

Palo Alto, California

COMPLETION DATE

2018

One of the largest geofoam projects Cell-Crete has been involved in within the last 10 years was the Lucile Packard Children’s Hospital. This included the installation of geofoam blocks in three garden areas and one lobby roof. Geofoam was mainly used to minimize the load amount applied on the building structure. The total amount of geofoam installed was above 18,000 CY of mostly EPS type 22 (Density 1.35 PCF [pounds per cubic foot]). Other EPS types (19, 29, & 46) were utilized as specified in the construction plans.

The Solution

Beginning in March of 2016, the approximation was 18 months of installation. Despite the volume, the most challenging area was the Discovery Garden. The complexity of the slab on the grade slope made it more difficult and time consuming to install the geofoam blocks. Each 4’x8′ block had to be trimmed in four different ways to later be placed and provide a flat surface. All the cut and trim for the geofoam was done on-site. The idea was to create a level surface to facilitate the installation of the next layer of blocks. The electrical conduits were another challenge with this project. Trenches needed to be created using geofoam for each electrical conduit. Subsequently, these trenches were filled and encapsulated with lightweight insulating concrete.

The Rainbow Garden and Dawes (previously known as Emerald) Garden were both similar in square footage, placing up to 30′ in height of geofoam blocks in some spaces. The amphitheater area, located on the west side of the Dawes Garden, consisted of two base layers of EPS 29 (4′ thick each) around shear keys, while the rest of the blocks consisted of EPS 22. This region was stair-stepped in 1′ increments, avoiding a slip plane for the soil.

This project was successfully completed without delays and all deadlines were met because of the 25–30 crew members who worked hard every single day. Cell-Crete Corporation is proud to have been part of this great project contributing to the community and children in need.

Cell-Crete-Crenshaw-Corridor-LAX-Transit-1-1200x900.jpg

Crenshaw Corridor/LAX Transit Project

About The Project

PROJECT LOCATION

Los Angeles, California

COMPLETION DATE

2017

Due to the increase in vertical pressure from the additional fill load for the embankment supporting the Metro’s track row, unreinforced concrete encasement for the Department of Water and Power (DWP) duct banks directly underneath were susceptible to settlement/cracking.

The Solution

The chosen backfill material was a low-density fill material in between Mechanically Stabilized Earth (MSE) walls. Cellular concrete substantially reduced the fill loads on the duct banks and eliminated the potential for damage/settlement to the existing DWP lines underground.

Cell-Crete-Gerald-Desmond-Bridge-2-1200x900.jpg

Gerald Desmond Bridge, Long Beach, CA

About The Project

PROJECT LOCATION

Long Beach, California

COMPLETION DATE

Ongoing

The Port of Long Beach is the owner of this design-build project. Cellular concrete was elected due to the presence of compressible material. Approaches to the bridge address settlement and stability consideration on the in-situ soil and the magnitude of the earthquake design. A total of over 200,000 CY have been placed on the project in 6 different locations, using precast panels with LCC as the backfill material.

The Solution

Class II and Class III material is being utilized on the east side approaches to the bridge. At the lower portions of the fill, Class II cellular concrete will be poured to maximize the load reduction. Class IV cellular concrete will be used at the uppermost layers (directly under the pavement). The design approach included treating the LCC material as embankment material and designing the structure as a typical length of MSE wall reinforcement. Steel ladder reinforcement and ribbed steel straps were used. No reported/observed performance issues or concerns have been encountered to date.

Cell-Crete-Emergency-Repair-Project-3.jpg

Mount Hamilton Road: Caltrans Emergency Road Repair

About The Project

PROJECT LOCATION

San Jose, California

CLIENT

California Department of Transportation (Caltrans)

COMPLETION DATE

2017

A mudslide completely washed out a section of Mount Hamilton Road in the hills above San Jose, CA, restricting travel to the Lick Observatory in the South Bay.

The Solution

Cell-Crete filled against the sheet pile with 31 PCF (pounds per cubic foot) (Class III) cast-density lightweight cellular concrete (LWCC) material and was able to restore Mount Hamilton Road.

CA-04-2.jpg

CA DOT: 04-2G9504

About The Project

PROJECT LOCATION

Winters, California

CLIENT

California Department of Transportation (Caltrans)

In 2015, Caltrans advertised a project to repair an unstable slope on Highway 128 (west of Winters, CA). According to the Preliminary Geotechnical Report (PGR) dated March 4th, 2014, the roadway was constructed on a poorly made fill slope that caused slip outs in the winter.

The PGR recommended removing the bulk of the slide debris and a portion of the underlying soil before reconstructing the fill slope with Expanded Polystyrene (EPS) Geofoam blocks. Replacing the poor material with EPS serves two functions: it increases shear strength of the low-strength, poorly compacted fill, and its light weight reduces the driving forces on the slide. Bid tabulations indicate that bid prices for the EPS ranged from $130/CY to $170/CY.

The Solution

Cell-Crete Corporation, as a subcontractor to the winning general contractor (GC), worked to submit a Cost Reduction Incentive Proposal (CRIP) to the State to replace the EPS blocks with Cell-Crete’s Lightweight Cellular Concrete (LCC). Cell-Crete’s LCC mixes cement slurry with a preformed foam to create a final product with a low unit weight and moderate strength. Once cured, the LWCC is similar to pumice. The mix design submitted had a cast density of 27 PCF (pounds per cubic foot) and an unconfined uniaxial compressive strength of 40 + PSI at 28 days.

San-Francisco-Airport-New-Terminal-2-1200x900.jpg

San Francisco Airport (SFO) New Terminal

About The Project

PROJECT LOCATION

San Francisco, California

COMPLETION DATE

2019

Cell-Crete Corporation was contracted to provide a lightweight insulating roof system for the San Francisco International Airport (SFO), which has now been covered almost entirely with solar panels.

The Solution

The lightweight cellular concrete (LCC) installed on the rooftop is 42 PCF (pounds per cubic foot), providing a great insulation factor and high strength for the 247,547 sq. ft. rooftop in South San Francisco. This material flows easily over the structure and completely encases the rooftop conduit and steel wire over the flat structural concrete and metal deck.