Portfolio

IMG_07892-copy-1200x825.jpg

Genesis Marina

Genesis Marina

PROJECT LOCATION

Brisbane, CA

The Project

This marina building project needed a material flowable enough to arrest all the electrical conduit lines in place, but strong enough to prevent cracking or damage over time. Access was difficult due to site logistics and the pour geometry. Heavy equipment could not be brought in to pour back in the trenches without damaging the utilities.

The Solution

The utility trenches were filled with lightweight cellular concrete and burrito wrapped once the material was cured to ensure the conduit lines were fully protected. Backfill material was then placed directly over the wrapped pour areas to finish the site and protect the electrical lines.

Project Assets

20220224_182831000_iOS1-1200x675.jpg

Pulte Homes Development

Pulte Homes Development

PROJECT LOCATION

Alameda, CA

The Project

Landfill sites provide a serious and complex challenge for any future land development, especially in Alameda. The entire site is built on a landfill and with rising tides plaguing the area, developers are finding it difficult to safely build multi-story structures. Excavations often experience water intrusion, compromised boundaries and sluffing of material, and geotechnical reports can easily miss extremely challenging soil conditions.

The Solution

To mitigate soil integrity issues, the entire site was excavated and the landfill material was removed and replaced with LCC. The areas where LCC was installed could support multi-story structures without risk of extreme or unexpected settlement due to the net neutral loading on the soil but overall, more consistent and controlled density of material.

Project Assets

East-End-of-Site-copy-1200x787.jpeg

Upper Conduit Repair

Upper Conduit Repair

PROJECT LOCATION

Salt Lake City, UT

The Project

Just off the East side of I-215 near exit 1 stands an iconic rock formation known as Suicide Rock at the mouth of Parley’s Canyon. This highly vandalized rock is a billboard for youthful rebellion, love, loss, and causes they support. The name is adopted from a local Native American legend of a Native American maiden who threw herself from this lookout point because her betrothed Brave was killed in battle.

A steep winding dirt service road with sharp turns along the Parley’s Creek and rock formations is the main access to this site where a new waterline was placed inside the older pipeline. These conditions made it impossible to get large equipment down to the bottom or to get trucks bearing any load back up the road after working on the annular fill inside the pipeline.

The Solution

LCC was the only solution to access these areas, maintain low injection pressures, flowability required, and the experience to fill the annular void in this pipeline. Our team met with their superintendent immediately after being contacted to discuss a pour plan. By dividing the fill into 4 separate sections with 5 injection points, we were able to run over 1000’ of hose to fill approximately 1400 LF of annular fill. This was achieved by staging our equipment in one location in the general contractor’s “yard” next to their water supply.

This was only one phase of the project. We look forward to the next phase and LCC going where no other lightweight flowable fill has gone before!

Project Assets

IMG_203985ffe154-2-1200x900.jpeg

Rasmussen Farms

Rasmussen Farms

PROJECT LOCATION

Draper, UT

The Project

Rasmussen Farms is farmland that is being turned into a new development with over 50 units. The site plan shows a 10” RCP sewer line that runs East to West into another condo/apartment complex then turned south from a manhole to the other site entrance. This run of pipe was just under 1,000 LF and they needed to abandon the line with flowable fill.

The Solution

LCC was selected to abandon the sewer line because of its flowability and our ability to batch it on site. We were able to stage our equipment in one location and pump uphill to the vented end of the sewer line. The general contractor prepared two manholes to allow the LCC to flow through them to the vent. This plan allowed us to pump LCC without having to add a second injection point in the condo/apartment property.

Project Assets

20220105_192439967_iOS-1-1200x801.jpg

March Air Reserve

March Air Reserve

PROJECT LOCATION

Riverside, CA

The Project

Boudreau Pipeline Corporation installed hundreds of feet of 7ft x 14f reinforced concrete box (RCB) near the March Air Force Museum located in Riverside, Ca. A lightweight material that would reduce surcharging and settlement was required for the backfill along the RCB over a 100 ft section.

The Solution

Cell-Crete Corporation was subcontracted to provide labor, materials, and equipment to install Lightweight Cellular Concrete (LCC) as backfill around the 100 ft RCB section. The material specified for backfill was Class IV LCC per California Department of Transportation Specification 19-8.01A. Over 2,000 CY of class IV LCC (40PCF, 120+psi) material was installed successfully. LCC was considered because expected minimal settlement, decrease of surcharge, and ease of installation. The work was completed with Cell-Crete Corporation’s mobile batch plant (small footprint) within four days.

Project Assets

IMG_18696b3312e5-1200x900.jpeg

Lifton Pump Station

Lifton Pump Station

PROJECT LOCATION

Bear Lake, ID

The Project

This project is located on the north shore of Bear Lake in Idaho. The pour was adjacent to an existing pump house and sheet piles next to the lake.

Lightweight Cellular Concrete (LCC) was used to reduce the lateral loads to the sheet piles and the dead load to the existing fill due to soil conditions at the lake’s edge. The LCC was poured over the area that previously had wood cribbing. The flowability and self-leveling characteristics helped to fill some of the complicated areas and provided a good elevation to reference to the fill benchmarks.

All cold weather pours require coordination with the general contractor to have a successful pour. There was significant snowfall nearly every day of the pour. Our crew coordinated with the general contractor to cover the pour area and monitor a heating system while the material cured. Together they were able to complete the pour despite the cold temperatures and weather challenges.

Project Assets

11.10.21-IMG_0276f50068bf-1200x900.jpeg

Porter Rockwell

Porter Rockwell

PROJECT LOCATION

Riverton, UT

The Project

Cell-Crete Corporation worked with Ralph L Wadsworth Construction (RLW) and their team to find a solution to reduce the load applied on top of the box culvert. Lightweight Cellular Concrete (LCC) was proposed to reduce the backfill load over a box culvert in the Utah Lake Distribution Canal. We explored several designs and discussed the cost and schedule for each design.

The engineer wanted to see how much load would be applied using LCC. The submittal process gave us the opportunity to cite some lab results on the curing process and how the weight was affected. A sample of LCC with a wet density of 27 pounds per cubic foot (PCF) would weigh less in 28 days. The water will evaporate, and the weight of the sample could

change as much as a few pounds. This would be affected by variables such as humidity, exposed surface, weather, soil conditions, etc.

The location of this project proved to be an ideal location to use LCC for load reduction. We were able to use 3-foot lifts and pour large sections over the box culvert. The general contractor would backfill around the LCC and form up the next lift. It was a pleasure to work with RLW and find yet another solution for load reduction using LCC.

Project Assets

DJI_0218-1200x675.jpg

Parcel J

Parcel J

PROJECT LOCATION

Oakland, CA

The Project

Cell-Crete partnered with Webcor Concrete to provide lightweight cellular concrete to this project on the waterfront in Oakland, CA. Building loading on the site made a heavy concrete footing a challenge, so our lightweight material was used to fill the gaps while still providing significant fill strength. Each blocked out area was filled with LCC in a sequence following an aggressive pour schedule.

Project Assets

IMG_1789-1200x900.jpg

Ash Creek Dam Outlet

Ash Creek Dam Outlet

PROJECT LOCATION

New Harmony, UT

The Project

This project was in New Harmony, UT near the Ash Creek Reservoir just off the north bound I-15. This was an annular fill project using 45 PCF lightweight cellular concrete (LCC). There was an arched tunnel in the native stone reaching over 230 linear feet into the mountain where it met with the previously completed section. A 42” pipe was installed by the general contractor, and we were asked to fill the void between the tunnel and the pipe.

The Solution

Coordinating a plan with the general contractor, dam safety, engineer, and the water district, we proposed using a series of grout lines and vents through a concrete bulkhead to fill the voids. Filling the pipe with water and the bulkhead helped prevent buoyancy. This plan was a success and saved the general contractor over a week on their schedule.

Project Assets

271765651_114130037752873_6394065183093167230_n.jpg

Ocean Blvd Project

Ocean Blvd Project

PROJECT LOCATION

Long Beach, CA

The Project

We recently completed the Ocean Blvd Project with The Port of Long Beach after they started construction on a new
bicycle/pedestrian bridge east of the Gerald Desmond Bridge off Pico Avenue. The goal was to convert the existing vehicle lanes into a two-way bicycle lane and assist with traffic flow.

The Solution

Cell-Crete poured lightweight cellular concrete (LCC) behind the MSE Walls of the bridge. LCC was specified as backfill for the project as it reduces the fill load under the bridge, resolves settlement concerns, and offers environmental protection.

Project Assets